27 FOOT DEEP SEWER TAP

A lot of thought and planning went into doing this sewer tap. At a depth of 27 feet deep, we accomplished one of the most difficult sewer taps. From start to finish it took us 6 days. It took over 350 tons of stone and gravel to backfill this hole. Once we Backfilled we ran the lateral through a parking lot 400 feet to the new building.